school: Lincoln Elementary School level: ES category: Replacement marker: orange_circle description: Built in 1955 cumulative_total: estimated_cost: target_year: 2017 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.215369, -115.112115 longitude: -115.112115 existing_portables: |
school: Bell Elementary School level: ES category: Replacement marker: orange_circle description: Built in 1963 cumulative_total: estimated_cost: target_year: 2017 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.140705, -115.180643 longitude: -115.180643 existing_portables: |
school: Ullom Elementary School level: ES category: Replacement marker: orange_circle description: Built in 1962 cumulative_total: estimated_cost: target_year: 2018 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.10401, -115.066458 longitude: -115.066458 existing_portables: |
school: Smith Middle School level: MS category: Replacement marker: orange_circle description: Built in 1952 cumulative_total: estimated_cost: target_year: 2018 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.191087, -115.123593 longitude: -115.123593 existing_portables: |
school: Fremont Middle School level: MS category: Replacement marker: orange_circle description: Built in 1955, the middle school is planned to be replaced with John C. Fremont Elementary. cumulative_total: estimated_cost: target_year: 2019 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.146954, -115.138954 longitude: -115.138954 existing_portables: |
school: Ira Earl Elementary School level: ES category: Replacement marker: orange_circle description: Built in 1964 cumulative_total: estimated_cost: target_year: 2019 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.185681, -115.072049 longitude: -115.072049 existing_portables: |
school: Mackey Elementary School level: ES category: Replacement marker: orange_circle description: Built in 1964 cumulative_total: estimated_cost: target_year: 2020 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.209286, -115.146597 longitude: -115.146597 existing_portables: |
school: Thomas Elementary School level: ES category: Replacement marker: orange_circle description: Built in 1963 cumulative_total: estimated_cost: target_year: 2020 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.125352, -115.130534 longitude: -115.130534 existing_portables: |
school: Wasden Elementary School level: ES category: Replacement marker: orange_circle description: Built in 1955 cumulative_total: estimated_cost: target_year: 2020 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.162393,-115.179876 longitude: -115.179876 existing_portables: |
school: Griffith Elementary School level: ES category: Replacement marker: orange_circle description: Built in 1962 cumulative_total: estimated_cost: target_year: 2021 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.168887, -115.200895 longitude: -115.200895 existing_portables: |
school: Sandy Valley Elementary School, Middle and High schools level: category: Phased replacement marker: orange_circle description: Phase 1 is in progress in the 2017 school year cumulative_total: estimated_cost: target_year: Phase 2 is in 2018 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 35.813289, -115.609615 longitude: -115.609615 existing_portables: |
school: Southeast Career and Technical Academy level: HS category: Phased replacement marker: orange_circle description: Phase 1 is completed cumulative_total: estimated_cost: target_year: Phase 2 is in 2019 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.081527, -115.069961 longitude: -115.069961 existing_portables: |
school: Hoggard Elementary School level: ES category: Phased replacement marker: orange_circle description: Phase 1 is completed cumulative_total: estimated_cost: target_year: Phase 2 is in 2021 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.18283, -115.169209 longitude: -115.169209 existing_portables: |
school: Twin Lakes Elementary School level: ES category: Phased replacement marker: orange_circle description: Phase 1 is completed cumulative_total: estimated_cost: target_year: Phase 2 is in 2021 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.18424, -115.186148 longitude: -115.186148 existing_portables: |
school: Boulder City High School level: HS category: Phased replacement marker: orange_circle description: Phase 1 is completed and phase 2 is in progress in the 2017 school year cumulative_total: estimated_cost: target_year: Phase 3 and 4 are in 2018 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 35.978222, -114.834512 longitude: -114.834512 existing_portables: |
school: Elementary school at Lamb and Kell level: ES category: New school in the city of North Las Vegas marker: ylw_circle description: Planned relief schools: Lincoln and Craig cumulative_total: estimated_cost: target_year: Opening 2017-18 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.1916193, -115.0808426 longitude: -115.0808426 existing_portables: |
school: Elementary school at La Madre and Lawrence level: ES category: New school in the city of North Las Vegas marker: ylw_circle description: Planned relief schools: Elizondo, Scott and Watson cumulative_total: estimated_cost: target_year: Opening 2019-20 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.2505999, -115.1235352 longitude: -115.1235352 existing_portables: |
school: Elementary school at Antelope Ridge level: ES category: New school in the city of Las Vegas marker: ylw_circle description: Planned relief schools: Bell cumulative_total: estimated_cost: target_year: Opening 2017-18 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.1760851, -115.3681532 longitude: -115.3681532 existing_portables: |
school: Elementary school at Farm and Jensen level: ES category: New school in the city of Las Vegas marker: ylw_circle description: Planned relief schools: Bozarth, Thompson, Darnell cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.2987737, -115.3152937 longitude: -115.3152937 existing_portables: |
school: Elementary school at Galleria and Dave Wood Circle level: ES category: New school in Henderson marker: ylw_circle description: Planned relief schools: Sewell, Hinman, Treem and Thorpe cumulative_total: estimated_cost: target_year: Opening 2017-18 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.0851222, -114.9617513 longitude: -114.9617513 existing_portables: |
school: Elementary school at Beltrada and Via Italia level: ES category: New school in Henderson marker: ylw_circle description: Planned relief schools: Wallin, Wolff, Schorr cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 35.949085, -115.1290744 longitude: -115.1290744 existing_portables: |
school: Elementary school at Chapata and Cassady Hollow level: ES category: New school in Henderson marker: ylw_circle description: Planned relief schools: Vanderburg, Twitchell, Kesterson cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.0267337, -115.04445 longitude: -115.04445 existing_portables: |
school: Elementary school East of Treem and Thorpe (site acquisition pending) level: ES category: New school in Henderson marker: ylw_circle description: Planned relief schools: Treem, Thorpe, Hinman and Galleria and Dave Wood cumulative_total: estimated_cost: target_year: Opening 2019-20 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.0761979, -115.0590101 longitude: -115.0590101 existing_portables: |
school: Elementary school at Maule and Grand Canyon level: ES category: New school in Clark County marker: ylw_circle description: Planned relief schools: Tanaka and Batterman cumulative_total: estimated_cost: target_year: Opening 2017-18 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.062788, -115.3242717 longitude: -115.3242717 existing_portables: |
school: Elementary school at Arville and Mesa Verde level: ES category: New school in Clark County marker: ylw_circle description: Planned relief schools: Ries, Fine, Wiener and Hill cumulative_total: estimated_cost: target_year: Opening 2017-18 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.0430326,-115.1941881 longitude: -115.1941881 existing_portables: |
school: Elementary school at Chartan and Pioneer level: ES category: New school in Clark County marker: ylw_circle description: Planned relief schools: Reedom and Wright cumulative_total: estimated_cost: target_year: Opening 2017-18 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 35.9876971, -115.2591726 longitude: -115.2591726 existing_portables: |
school: Elementary school at Spencer and Pyle level: ES category: New school in Clark County marker: ylw_circle description: Planned relief schools: Schorr, Bass, Hummel, Cartwright, Beatty, Roberts cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.005447,-115.1264497 longitude: -115.1300291 existing_portables: |
school: Elementary school at Dean Martin and I-15 level: ES category: New school in Clark County marker: ylw_circle description: Planned relief schools: Ries, Frias, Stuckey cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.0458295, -115.19011 longitude: -115.19011 existing_portables: |
school: Elementary school at Ford and Riley level: ES category: New school in Clark County marker: ylw_circle description: Planned relief schools: Forbuss, Steele, Fine cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.0299067, -115.2878147 longitude: -115.2878147 existing_portables: |
school: Elementary school at El Capitan and Gomer level: ES category: New school in Clark County marker: ylw_circle description: Wright cumulative_total: estimated_cost: target_year: Opening 2019-20 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.0101509, -115.2912615 longitude: -115.2912615 existing_portables: |
school: Elementary school at Vegas Valley and Hollywood level: ES category: New school in Clark County marker: ylw_circle description: Planned relief schools: Iverson, Hal Smith and Mendoza cumulative_total: estimated_cost: target_year: Opening 2019-20 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.1381251,-115.0353129 longitude: -115.0353129 existing_portables: |
school: Elementary school at Tompkins and El Conquistador level: ES category: New school in Clark County marker: ylw_circle description: Planned relief schools: Batterman, Rogers and Hayes cumulative_total: estimated_cost: target_year: Opening 2019-20 school year classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: longitude: existing_portables: |
school: Chaparral High School level: HS category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component Replacement cumulative_total: 37,045,000 estimated_cost: 11,900,000 target_year: Available funds 2015-17 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.12031, -115.085724 longitude: -115.085724 existing_portables: |
school: Las Vegas Academy High School level: HS category: Mechanical system upgrades marker: ltblu_circle description: HVAC, Roof, LAN, Electrical, Low Voltage cumulative_total: 131,785,000 estimated_cost: 25,410,000 target_year: Available funds 2017-19 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.164882, -115.139375 longitude: -115.139375 existing_portables: |
school: Palo Verde High School level: HS category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component and Roof Replacement cumulative_total: 89,715,000 estimated_cost: 11,400,000 target_year: Available funds 2017-19 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.171999, -115.334707 longitude: -115.334707 existing_portables: |
school: Bonanza High School level: HS category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component and Roof Replacement cumulative_total: 106,375,000 estimated_cost: 11,100,000 target_year: Available funds 2017-19 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.153561, -115.236683 longitude: -115.236683 existing_portables: |
school: Cartwright Elementary School level: ES category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component Replacement cumulative_total: 95,275,000 estimated_cost: 2,795,000 target_year: Available funds 2017-19 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.015996, -115.139953 longitude: -115.139953 existing_portables: |
school: Cambeiro Elementary School level: ES category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component and Roof Replacement cumulative_total: 92,480,000 estimated_cost: 2,765,000 target_year: Available funds 2017-19 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.178426, -115.110856 longitude: -115.110856 existing_portables: |
school: Lyon Middle School level: MS category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component Replacement cumulative_total: 133,905,000 estimated_cost: 2,120,000 target_year: Available funds 2017-19 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.584875, -114.447239 longitude: -114.447239 existing_portables: |
school: Moapa Valley High School level: HS category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component and Roof Replacement cumulative_total: 158,410,000 estimated_cost: 13,500,000 target_year: Available funds 2019-20 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.584971, -114.459613 longitude: -114.459613 existing_portables: |
school: Desert Pines High School level: HS category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component and Roof Replacement cumulative_total: 189,195,000 estimated_cost: 10,590,000 target_year: Available funds 2019-20 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.178238, -115.092901 longitude: -115.092901 existing_portables: |
school: Eldorado High School level: HS category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component and Roof Replacement cumulative_total: 144,910,000 estimated_cost: 9,870,000 target_year: Available funds 2019-20 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.180364, -115.048421 longitude: -115.048421 existing_portables: |
school: Garside Middle School level: MS category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component and Roof Replacement cumulative_total: 166,110,000 estimated_cost: 7,700,000 target_year: Available funds 2019-20 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.169222, -115.234206 longitude: -115.234206 existing_portables: |
school: Keller Middle School level: MS category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component and Roof Replacement cumulative_total: 178,605,000 estimated_cost: 7,085,000 target_year: Available funds 2019-20 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.165077, -115.036437 longitude: -115.036437 existing_portables: |
school: Gibson Middle School level: MS category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component and Roof Replacement cumulative_total: 196,410,000 estimated_cost: 6,135,000 target_year: Available funds 2019-20 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.182265, -115.196562 longitude: -115.196562 existing_portables: |
school: Richard Bryan Elementary School level: ES category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component and Roof Replacement cumulative_total: 168,885,000 estimated_cost: 2,775,000 target_year: Available funds 2019-20 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.194298, -115.268148 longitude: -115.268148 existing_portables: |
school: Robison Middle School level: MS category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component Replacement cumulative_total: 171,520,000 estimated_cost: 2,635,000 target_year: Available funds 2019-20 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.178683, -115.070172 longitude: -115.070172 existing_portables: |
school: Keller Elementary School level: ES category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component cumulative_total: 198,280,000 estimated_cost: 1,400,000 target_year: Available funds 2019-20 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.169539, -115.054332 longitude: -115.054332 existing_portables: |
school: McCall Elementary School level: ES category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component Replacement cumulative_total: 135,040,000 estimated_cost: 1,135,000 target_year: Available funds 2019-20 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.204036, -115.130712 longitude: -115.130712 existing_portables: |
school: Hancock Elementary School level: ES category: Mechanical system upgrades marker: ltblu_circle description: HVAC Component Replacement cumulative_total: 190,275,000 estimated_cost: 1,080,000 target_year: Available funds 2019-20 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.152643, -115.215625 longitude: -115.215625 existing_portables: |
school: Las Vegas High School level: HS category: Mechanical system upgrades marker: ltblu_circle description: Boilers cumulative_total: 196,880,000 estimated_cost: 470,000 target_year: Available funds 2019-20 classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.146395, -115.03139 longitude: -115.03139 existing_portables: |
school: Fyfe Elementary School level: ES category: Closure marker: red_circle description: Built in 1963 cumulative_total: estimated_cost: target_year: classroom_addition: current_rooms: program_capacity: total_enrolled: latitude: 36.177357, -115.194915 longitude: -115.194915 existing_portables: |
school: Tate Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: 18 and a multipurpose room current_rooms: 36 program_capacity: 509 total_enrolled: 826 latitude: 36.20407, -115.084706 longitude: -115.084706 existing_portables: 14 |
school: Bonner Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: 22 current_rooms: 31 program_capacity: 584 total_enrolled: 883 latitude: 36.18105, -115.323783 longitude: -115.323783 existing_portables: 17 |
school: Crestwood Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: 22 current_rooms: 31 program_capacity: 437 total_enrolled: 703 latitude: 36.154797, -115.12801 longitude: -115.12801 existing_portables: 10 |
school: Cunningham Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: 18 current_rooms: 35 program_capacity: 532 total_enrolled: 840 latitude: 36.113792, -115.052571 longitude: -115.052571 existing_portables: 14 |
school: Detwiler Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: 14 current_rooms: 531 program_capacity: 514 total_enrolled: 782 latitude: 36.194718, -115.180696 longitude: -115.180696 existing_portables: 10 |
school: Fong Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: 18 current_rooms: 34 program_capacity: 494 total_enrolled: 873 latitude: 36.200546, -115.236411 longitude: -115.236411 existing_portables: 17 |
school: Harris Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: 18 and a multipurpose room current_rooms: 36 program_capacity: 514 total_enrolled: 722 latitude: 36.123474, -115.090927 longitude: -115.090927 existing_portables: 10 |
school: Hewetson Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: 14 current_rooms: 40 program_capacity: 633 total_enrolled: 1002 latitude: 36.176503, -115.122417 longitude: -115.122417 existing_portables: 19 |
school: Lowman Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: 22 current_rooms: 32 program_capacity: 525 total_enrolled: 887 latitude: 36.237285, -115.066686 longitude: -115.066686 existing_portables: 17 |
school: Squires Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: 14 current_rooms: 37 program_capacity: 530 total_enrolled: 736 latitude: 36.192687, -115.122316 longitude: -115.122316 existing_portables: 13 |
school: Beckley Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Mid-year 2017-18 classroom_addition: 18 current_rooms: 36 program_capacity: 561 total_enrolled: 903 latitude: 36.131623, -115.100104 longitude: -115.100104 existing_portables: 19 |
school: Clyde Cox Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Mid-year 2017-18 classroom_addition: 22 current_rooms: 33 program_capacity: 492 total_enrolled: 790 latitude: 36.230556, -115.095199 longitude: -115.095199 existing_portables: 22 |
school: Craig Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Mid-year 2017-18 classroom_addition: 14 current_rooms: 37 program_capacity: 519 total_enrolled: 794 latitude: 36.224047, -115.113353 longitude: -115.113353 existing_portables: 17 |
school: Culley Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Mid-year 2017-18 classroom_addition: 18 current_rooms: 36 program_capacity: 570 total_enrolled: 864 latitude: 36.183818, -115.221401 longitude: -115.221401 existing_portables: 18 |
school: Dearing Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Mid-year 2017-18 classroom_addition: 18 current_rooms: 36 program_capacity: 530 total_enrolled: 840 latitude: 36.134653, -115.078412 longitude: -115.078412 existing_portables: 18 |
school: Dondero Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Mid-year 2017-18 classroom_addition: 14 and a multipurpose room current_rooms: 34 program_capacity: 523 total_enrolled: 801 latitude: 36.108054, -115.228311 longitude: -115.228311 existing_portables: 9 |
school: Herr Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Mid-year 2017-18 classroom_addition: 14 current_rooms: 38 program_capacity: 526 total_enrolled: 721 latitude: 36.20193, -115.031997 longitude: -115.031997 existing_portables: 11 |
school: Lake Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Mid-year 2017-18 classroom_addition: 14 current_rooms: 38 program_capacity: 516 total_enrolled: 889 latitude: 36.139273, -115.12868 longitude: -115.12868 existing_portables: 20 |
school: Long Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Mid-year 2017-18 classroom_addition: 22 current_rooms: 32 program_capacity: 413 total_enrolled: 848 latitude: 36.150061, -115.088754 longitude: -115.088754 existing_portables: 21 |
school: Ronzone Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Mid-year 2017-18 classroom_addition: 18 current_rooms: 36 program_capacity: 535 total_enrolled: 952 latitude: 36.196786, -115.217734 longitude: -115.217734 existing_portables: |
school: Hal Smith Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Mid-year 2017-18 classroom_addition: 22 current_rooms: 31 program_capacity: 535 total_enrolled: 936 latitude: 36.130508, -115.062865 longitude: -115.062865 existing_portables: 16 |
school: Woolley Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Mid-year 2017-18 classroom_addition: 22 current_rooms: 31 program_capacity: 407 total_enrolled: 792 latitude: 36.231462,-115.094626 longitude: -115.094626 existing_portables: |
school: Wynn Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Mid-year 2017-18 classroom_addition: 18 current_rooms: 32 program_capacity: 459 total_enrolled: 871 latitude: 36.13592,-115.219241 longitude: -115.219241 existing_portables: |
school: Bunker Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: 22 current_rooms: 31 program_capacity: 537 total_enrolled: 843 latitude: 36.21166, -115.232964 longitude: -115.232964 existing_portables: 10 |
school: Edwards Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: 18 and a multipurpose room current_rooms: 34 program_capacity: 492 total_enrolled: 819 latitude: 36.170912, -115.074663 longitude: -115.074663 existing_portables: 9 |
school: Katz Elementary School level: ES category: Classroom additions marker: grn_circle description: cumulative_total: estimated_cost: target_year: Opening 2018-19 school year classroom_addition: 18 current_rooms: 32 program_capacity: 474 total_enrolled: 741 latitude: 36.191344, -115.247892 longitude: -115.247892 existing_portables: 12 |